Question
15 male employees or 20 female employees of a company can complete a project in 26 days. How long will 30 male employees and 12 female employees together take to complete the project?
More Time Questions
- What is the angle traced by the hour hand in 23 minutes?
- Numan does half as much work as Gagan in four-fifth of the time. If together they take 16 days to complete a work, how much time shall Gagan take to do it?
- A motorboat whose speed is 20 km/h in still water takes 30 minutes more to go 24 km upstream than to cover the same distance downstream. If the speed of th...
- A trip from Mumbai to Pune takes 4 hours 30 minutes at a speed of 60 km/hr. How long (in hours) will it take to complete, if the speed is 15m/sec?
- A and B can do a work in 21 days, A is (7/4) times as efficient as B. In how many days, A alone can complete the (100/3)% of the work?
- A and B together can complete a task in 10 days, B and C can do in 15 days, and C and A together can do it in 12 days. How long will they take to complete ...
- A can cultivate 3/5th of the land in 15 days and B can cultivate 1/4th of the land in 10 days. In how many days working together A and B can cultivate 13/2...
- Hema takes a total of 9 hours 55 min to walk a certain distance and then cycling back to the same place from where she had started. She could walk both way...
- Harish and Bimal can complete a task in 20 days. They worked at it for 15 days and then Bimal left. The remaining work was done by Harish alone, in 10 days...
- A can complete a certain work in 30 days. B is 25% more efficient than A and C is 20% more efficient than B. They all worked together for 3 days. B alone w...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)