15 male employees or 20 female employees of a company can complete a project in 26 days. How long will 30 male employees and 12 female employees together take to complete the project?
15 males × 26 days = 20 females × 26 days ∵ 15 males = 20 females ∴ 30 males = 40 females Total work in terms of females = 20 females × 26 days = 520 units No of days taken by 30 males and 12 females: ⇒ (40 females + 12 females) = 52 females ∴ No of days taken = 520 units /52 females = 10 days
Which of the following statement is not correct regarding the description of Parenchyma tissue?
Light intensity at which photosynthesis and respiration are equal is known as:
The soil formation equation, S = f (cl, o, r, p, t….) was first formulated by:
The inflorescence of sugarcane is known as:
Type of silviculture system which can regenerate through seeds and majority have a long life is ___
Given below are two statements:
Statement I - Crop cafeteria is the demonstration of identified efficient crops in an agro-metrological region ...
Carrot belongs to the family:
Pusa Himani is a variety of:
Which one of the following is not a physical indicator of soil?
Chemiosmotic theory was first put forward by