Question
15 male employees or 20 female employees of a company
can complete a project in 26 days. How long will 30 male employees and 12 female employees together take to complete the project?Solution
15 males × 26 days = 20 females × 26 days β΅ 15 males = 20 females ∴ 30 males = 40 females Total work in terms of females = 20 females × 26 days = 520 units No of days taken by 30 males and 12 females: ⇒ (40 females + 12 females) = 52 females ∴ No of days taken = 520 units /52 females = 10 days
FSSAI launched The Eat Right India Movement on
CCS National Institute of Agriculture Marketing is situated in _________.
P rocess of drop down of milk after the stimulation of oxytocin
Current location of IRRI is ____
βAaj se thoda kamβ is awareness campaign to eliminate trans fats by 2022. Which of the following is not part of this?
Which is true for CAP.
What is the main objective of the Horticulture Mission for North East and Himalayan States (HMNEH)?
Which type of irrigation utilizes floodwater effectively for agricultural purposes?
Toxic compound found in almond is
In gene banks biodiversity is conserved for use by