Question
P and Q can complete a project in 15 days and 10 days,
respectively. They started doing the work together, but after 2 days, Q had to leave and P alone completed the remaining work. In how many days was the whole work completed?Solution
The correct answer is C
Which ministry oversees the Swachh Bharat Mission - Urban (SBM-Urban)?
The Non-traditional Skilling sub-component of PM VIKAS offers training in job roles compliant with which framework?
The International Monetary Fund (IMF) has approved $_____ billion in emergency support for Ukraine to finance expenditures and shore up the balance of p...
Which statements correctly describe the features of the SBI MSME Sahaj loan facility?
1. The loan process from application to disbursement is les...
The change in India’s net tax revenue during Apr–Jul 2025 was:
Which nation has launched the Chang’e-6 probe on a mission to collect samples from the far side of the Moon?
Which ideology guides the Bharatiya Adim Jati Sevak Sangh, which marked its 75th anniversary in 2024?
What was the fiscal deficit target as a percentage of GDP for FY25 set by the Indian government?
- Which benefit will Indian Railways introduce in February 2025 to lower coal transportation costs in RSR mode?
_______ has  signed an MoU with the Central TB Division ( CTD ) under the Ministry of Health and Family Welfare ( MoH&FW ) to undertake an intensified...