Question

A can do (2/5) of a work in 6 days and B can do 30% of the same work in 3 days. They worked together for 4 days. The remaining work was completed by C alone in 6 days. B and C together can complete 70% of the original work in:

A 5(1/2) days Correct Answer Incorrect Answer
B 4 days Correct Answer Incorrect Answer
C 5 days Correct Answer Incorrect Answer
D 4(1/2) days Correct Answer Incorrect Answer

Solution

A can complete the whole work in 6 × 5/2 = 15 days B can complete the whole work in 3 × 100/30 = 10 days Let the total unit of work be 30 unit (LCM of 15 and 10) Efficiency of A = 30/15 = 2 unit/day Efficiency of B = 30/10 = 3 unit/day Work done by A and B in 4 days = (2 + 3) x 4 = 20 unit Remaining work = 30 - 20 = 10 units Let the remaining work completed by C in x days 6 x x = 10 x = 10/6 B and C together can complete 70% of the original work in 30/(3 + 10/6) x 70/100 = 4 (1/2) days

Practice Next

Relevant for Exams:

×
×