A can finish a piece of the work in 16 days and B can
finish it in 12 days. They worked together for 4 days and then A left. B finished the remaining work. For how many total number of days did B work to finish the work completely?Solution
Total work = 48 (LCM of 16 and 12) Efficiency = Work/Time Total efficiency = 3 + 4 = 7 units Remaining work after 4 days = 48 - (7 × 4) = 48 - 28 = 20 units Time is taken by B to finish the remaining work = 20/4 = 5 days Total number of days B work = 4 + 5 = 9 days ∴ B work the total number 9 days to finish the work completely.
According to a report by prominent online blogging platform soic.in,which state in India has emerged as the largest economy with the highest GDP share i...
FDI in insurance sector in India is allowed till what extent ?
What is the percentage of protected workmen based on the total number of workmen employed in an establishment?Â
Which of the following are the key actors in industrial relations according to Dunlop's System Theory?Â
Market imperfections of a country are reflected in___________.
Which of the following statement is/are incorrect about “Gross Domestic Product”?
I.        Gross Domestic Product (GDP) is that i...
Which Indian city was recently ranked the 12th richest city globally?
The recent fall in international crude oil price has the highest impact on which of the following indicators?
...
What is Demand Pull Inflation?
What is the main objective of the Pradhan Mantri Jan Dhan Yojana?