Question
A can finish a piece of the work in 16 days and B can finish it in 12 days. They worked together for 4 days and then A left. B finished the remaining work. For how many total number of days did B work to finish the work completely?
More Time Questions
- A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days,respectively. B and C started the work and worked for 3 days and left....
- A and B can complete a piece of work in 120 days, B and C can complete it in 150 days, and A and C can complete it in 200 days. In how many days can B alon...
- A can complete 40% of a work in 6 days and B can complete 33(1/3)% of the same work in 8 days. They work together for 8 days. C alone completes the remaini...
- Pipes A and B can fill an empty tank in 6 and 8 hours respectively, while pipe C can empty the full tank in 10 hours. If all three pipes are opened togethe...
- A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take ...
- Question 6
- A car is moving at a uniform speed of 35 km/h. What is the time it takes to cover 140 km?
- A person from the top of a hill observes a vehicle moving towards him at a uniform speed. It takes 10 minutes for the angle of depression to change from 45...
- Two trains of length 200m and 160m respectively are running on parallel lines of rails. When running in the same direction the faster train passes the slow...
- A can cultivate 3/5th of the land in 15 days and B can cultivate 1/4th of the land in 10 days. In how many days working together A and B can cultivate 13/2...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)