Question

Working together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?

A 60 Correct Answer Incorrect Answer
B 90 Correct Answer Incorrect Answer
C 72 Correct Answer Incorrect Answer
D 120 Correct Answer Incorrect Answer
E none of these Correct Answer Incorrect Answer

Solution

Given that three people together can do the work in 24 days (1/a)+(1/b)+(1/c)=1/24 Also given (1/b) +(1/c)=1/36 1/a =1/24 - 1/36 1/a =(3-2)/72 a=72 days (1/72)+(1/b)=1/40 (1/b)=(1/40)-(1/72) (1/b)=9-5/360 1/b =1/90 b=90 days