Question
A can complete 25% of the work in 4 days, B can
complete 50% of the same work in 12 days and C can complete the same work in 32 days. They staned working together but C left after 4 days of the start and A left 6 days before the completion of the work. In how many days was the work completed?Solution
The correct answer is B
How many freedoms are covered under Art. 19 of the Indian Constitution?
How does K.C. Davis define Administrative law?
The Madrid Protocol is an international treaty that facilitates the registration and management of:
As per the IBC, 2016 a Financial Creditor means______________
The power of supreme court to transfer cases and appeals from one High Court to another High Court can be exercised on an application by :
Who is the Ex-officio chairman of the Council of States?
What is estoppel?Â
Any fact is relevant which shows or constitutes:
Regarding the awards of the Permanent Lok Adalat under the Legal Services Authorities Act, which of the following statements is correct?
Every agreement in restraint of the marriage of any person_________