      A can complete 25% of the work in 4 days, B can

      complete 50% of the same work in 12 days and C can complete the same work in 32 days. They staned working together but C left after 4 days of the start and A left 6 days before the completion of the work. In how many days was the work completed?
      A 10 days Correct Answer Incorrect Answer
      B 12 days Correct Answer Incorrect Answer
      C 8 days Correct Answer Incorrect Answer
      D 14 days Correct Answer Incorrect Answer

      Solution

      The correct answer is B