A can complete 25% of the work in 4 days, B can complete 50% of the same work in 12 days and C can complete the same work in 32 days. They staned working together but C left after 4 days of the start and A left 6 days before the completion of the work. In how many days was the work completed?
More Time Questions
- A flight has to travel between 2 cities A and B, 2000 km apart. The flight was slowed down due to bad weather. Its average speed for the trip reduced by 20...
- A can do a piece of work in 15 days while B can do it in 18 days. Starting with A, they work on alternate days till the work gets over. How many days in al...
- In a 200 m race, P beats Q by 35 m or 7 seconds. What is P's time over the course?
- Numan does half as much work as Gagan in four-fifth of the time. If together they take 16 days to complete a work, how much time shall Gagan take to do it?
- 15 male employees or 20 female employees of a company can complete a project in 26 days. How long will 30 male employees and 12 female employees together t...
- Working together A and B can do a job in 40 days, B and C in 36 days and all three together in 24 days. In how many days can B alone do the job?
- A can complete 40% of a work in 6 days and B can complete 33(1/3)% of the same work in 8 days. They work together for 8 days. C alone completes the remaini...
- A, B and C can do a job working alone in 50, 75 and 20 days respectively. They all work together for 4 days, then C quits. How many days will A and B take ...
- A started a work such that he can complete the whole work in 30 hours. After working for 10 hours, he worked with the rate such that the whole work can be ...
- A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days,respectively. B and C started the work and worked for 3 days and left....
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)