Question
Sanjay and Amit can do a piece of work in 8 days. Amit alone can do it in 12 days. In how many days will Sanjay do it alone?
More Time Questions
- A and B can do a work in 21 days, A is (7/4) times as efficient as B. In how many days, A alone can complete the (100/3)% of the work?
- A can complete a certain work in 30 days. B is 25% more efficient than A and C is 20% more efficient than B. They all worked together for 3 days. B alone w...
- Girish can paint a picture in 4 days when he works for 8 hours per day. Due to illness, he could work for only 6 hours per day and was required to finish p...
- A car is moving at a uniform speed of 35 km/h. What is the time it takes to cover 140 km?
- A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in 12 days. If ‘B’ takes 20 days to complete the work a...
- Numan does half as much work as Gagan in four-fifth of the time. If together they take 16 days to complete a work, how much time shall Gagan take to do it?
- A can complete 25% of the work in 4 days, B can complete 50% of the same work in 12 days and C can complete the same work in 32 days. They staned working t...
- A started a work such that he can complete the whole work in 30 hours. After working for 10 hours, he worked with the rate such that the whole work can be ...
- P, Q and R can complete a work in 10 days. 20 days and 30 days, respectively, working alone. How soon can the work be completed if P is assisted by Q and R...
- Two trains of length 200m and 160m respectively are running on parallel lines of rails. When running in the same direction the faster train passes the slow...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)