Question
A and B alone can complete a work in 30 and 60 days,
respectively. 50% of the work is completed by C in 6x days, and the remaining work is completed by A and B working together in ‘x’ days. Find the time taken by B and C to complete the whole work while working together.Solution
Time taken by A and B to complete the whole work while working together = (30 × 60)/(30 + 60) = 20 days So, x = 20/2 = 10 (Since, 50% of the work is done by A and B together) As, time taken by C to complete 50% of the work = 10 × 6 = 60 days So, time taken by C to complete the entire work = 60 × 2 = 120 days Therefore, time taken by B and C to complete the whole work while working together = (120 × 60)/(120 + 60) = 40 days
The sealing in aseptic packaging is known as __________
With respect to irradiation of food, which one of the following is INCORRECT:
__________ is an example Bio drainageÂ
Which of the following antibiotics component in corn leaves affects European corn borer?
Which one of the following statements is INCORRECT with respect to mass spectrometry?
What is the major use of Cashew Nut Shell Liquid (CNSL)?
Rice contains __% protein. Rice protein is known as ___
What is the term for a soil structure that is characterized by horizontal layers or plates of soil particles?
……………………..organisms that are capable of growth and reproduction in low temperatures, ranging from −20 °C to +10 °C. They are found ...
Which of the following elements is classified as an immobile nutrient in soil?