Question
A and B alone can complete a work in 30 and 60 days,
respectively. 50% of the work is completed by C in 6x days, and the remaining work is completed by A and B working together in ‘x’ days. Find the time taken by B and C to complete the whole work while working together.Solution
Time taken by A and B to complete the whole work while working together = (30 × 60)/(30 + 60) = 20 days So, x = 20/2 = 10 (Since, 50% of the work is done by A and B together) As, time taken by C to complete 50% of the work = 10 × 6 = 60 days So, time taken by C to complete the entire work = 60 × 2 = 120 days Therefore, time taken by B and C to complete the whole work while working together = (120 × 60)/(120 + 60) = 40 days
Which country has the longest written constitution in the world?
Which type of insurance policy that covers property that is easily movable and provides additional coverage over what normal insurance policies do not?
Under the current Consolidated FDI Policy, what is the maximum limit for Foreign Direct Investment (FDI) allowed under the automatic route for the solar...
What is the amount of compensation that is to be paid to an employee who is totally and permanently disabled as a result from injury under the provision...
Which of the following options gives the correct chronological order of rulers of the Mauryan Empire?
Which institution was established in 2015, in the place of Planning commission of India?Â
Whose autobiography is titled 'Born Again on the Mountain: a story of losing everything and finding it back'?
What is the primary function of a commercial bank?
The Jawaharlal Nehru Port is situated in which of the following cities?
Where can Nar Narayan Cave be found?