Question
Jack is twice efficient as Jill and Jill can do a piece of work in 30 days. Jill started the work and after a few days Jack joined him. They completed the work in 22 days. From the starting, for how many days they worked together?
More Time and work Questions
- "Amit" and "Bhanu" have respective completion times of 20 and 30 days for a task. They began working together on the project, but after a few days, "Amit" ...
- A’ and ‘B’ together can complete a work in 20 days while ‘A’ takes 25 days to complete the same work alone. If ‘C’ is 60% more efficient than ‘B’, then fin...
- P’s 3 days work is equal to Q’s 4 days work. If P and Q together can complete the work in 32 days then how much time Q will take to complete 75% of the wor...
- A can complete 25% of work in five days. And this takes four days more than B to complete the whole work. They started the work together but after X days A...
- 24 men can complete _______% of the whole work in 12 days working 10 hours in a day. 30 men working 8 hours in a daycan complete 30% of the whole work in _...
- A can finish a piece of work in 6 days and B can finish it in 12 days. In how many days will they finish the work together?
- The time taken by ‘A’ to complete a task is 6 days more than the time taken by A and B together. If A is twice as efficient as B, find the time required by...
- A can do a work in 15 days, B in 20 days. They start together, but A leaves after 4 days. In how many days is the work completed?
- Ajay, Bablu and Chirag can complete a certain work in 21, 28 and 15 days respectively. Ajay and Chirag started the work while Bablu joined them after 3 da...
- A team of 32 men and 28 women can complete a task in 60 days. When an additional eight men join the team, they are able to finish (4/5) of the same task in...