Question
Jack is twice efficient as Jill and Jill can do a piece of work in 30 days. Jill started the work and after a few days Jack joined him. They completed the work in 22 days. From the starting, for how many days they worked together?
More Time and work Questions
- A can complete a piece of work in 12 days and B can complete it in 18 days. They work together for 4 days and then B leaves. In how many more days will A f...
- A can do a work in 15 days, B in 20 days. They start together, but A leaves after 4 days. In how many days is the work completed?
- A and B together can do a piece of work in (p-8.8) days.The efficiency of D is 10% less than the efficiency of B. A and C together can do the same piece of...
- 'Akshay' alone takes 18 days to finish a work while 'Bhim' alone takes 24 days to finish the same work. If 'Akshay' and 'Bhim' work on alternate days start...
- ‘M’ is 60% more efficient than ‘N’. ‘N’ started the work alone and worked for 12 days and after that ‘N’ is replaced by ‘M’. If the total work is completed...
- Two friends, Aman and Vivek started a project together. They worked together for the first 6 days, but only 30% of the project was completed. Therefore, bo...
- John does ½ piece of work in 3 hours, Joe does ¼ of the remaining work in 1 hour and George finishes remaining work in 5 hours. How long would it have tak...
- Ashish and Anil can do a piece of work in 15 days and 20 days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the r...
- 5 men and 1 boy together can complete a work in 25 days. 3 men and 5 boys can together complete half of the same work in 10 days. Find the time taken by 1 ...
- Ram can do a piece of work in 50 days. He alone worked at it for 20 days and then Lakshman completed alone the rest work in 30 days. In how many days, they...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)