Question
Jack is twice efficient as Jill and Jill can do a piece
of work in 30 days. Jill started the work and after a few days Jack joined him. They completed the work in 22 days. From the starting, for how many days they worked together?Solution
Jill Jack Efficiency 1 : 2 Jill can do this job in 30 days so let total work = 1×30 = 30 units So let Jill work alone for x days and they work together for remaining i,e. (22-x) Hence 1×x+3(22-x) = 30 x +66 - 3x = 30 36 = 2x So x = 18 days So they work togethr for (22-x) i.e . 4 days
Why was Tom Cruise awarded the US Navy’s Distinguished Public Service Award?
India has recently agreed to bring down the import duty on some fresh and processed food items to settle the dispute between New Delhi & Washington at W...
Which financial institution partnered with Tata Power Solar Systems Ltd to facilitate financing options for installing rooftop solar panels and electric...
What is the primary goal of Tata Power’s $4.25 billion MoU with the Asian Development Bank (ADB)?
- Which Indian bank introduced the ‘PM SVANidhi Street Vendor Loan Monitoring System’ for better tracking of loans under the scheme?
What is the estimated cost of the Indo-Russian Vande Bharat sleeper train project, including manufacturing and maintenance?
Which Indian state is set to become the country’s first digitally literate state on August 21, 2025?Â
The AI-based monsoon forecasting system launched by the Ministry of Earth Sciences will provide forecasts up to:Â
Which of the following is/are the beneficiaries under the Pradhan Mantri Awas Yojana (Gramin):
I. People belonging to SCs/STs
II. Freed ...
- Which traditional musical instrument from Varanasi was awarded the GI tag in April 2025?