Question
A company has 7 men and 14 women who together can complete a job in 10 days. A woman takes twice as much time as a man to do the same job. How many days will 4 men take to complete the job?
More Time and work Questions
- If ‘P’ can complete a task in 24 days and ‘P’ with ‘Q’ together can finish it in 15 days, then how many days will ‘Q’ take to complete the work alone?
- Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' and...
- ‘M’ alone can complete a work in 18 days. ‘N’ is 50% as efficient as ‘M’. How long will they take to complete the work together?
- ‘A’ and ‘B’ can complete a certain work in 15 days and 10 days, respectively. They started working together and worked till completion of the work for whic...
- A can finish a work in 12 days and B can finish the same work in 18 days. They work together for 4 days and then B leaves. In how many more days can A alon...
- 1 man and 3 boys can together complete a work in 20 days. 2 men and 3 boys can together complete the same work in 15 days. Find the time taken by 6 boys to...
- X can work as fast as Y and Z together. X and Y together can finish the same task 3 times as fast as Z. If all three working together can finish the task i...
- 55 men can complete a piece of work in 12 days. 15 men started the same work and worked for 10 days, and then joined by ‘x’ more men such that the remainin...
- 'A' alone can do some work in 15 days. 'B' is 40% more efficient than 'A'. 'A' worked alone for 8 days and left. How much time (in days) does 'B' need to f...
- Armaan can complete a task in 36 days, Bittu in 45 days, and Chirag in 60 days. If Bittu and Chirag together work on the task for 10 days, how many additio...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt