📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      ‘M’ alone can complete a work in 18 days. ‘N’ is

      50% as efficient as ‘M’. How long will they take to complete the work together?
      A 15 days Correct Answer Incorrect Answer
      B 22 days Correct Answer Incorrect Answer
      C 18 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer

      Solution

      ATQ,

      Let the efficiency of ‘M’ = 6x units/day

      Then, total work = 6x × 18 = 108x units

      Efficiency of ‘N’ = 6x × 0.5 = 6x × (1/2) = 3x units/day

      So, combined efficiency of ‘M’ and ‘N’ = 6x + 3x = 9x units/day

      So, time taken by ‘M’ and ‘N’ together to complete the work = 108x / 9x = 12 days

      Practice Next
      ask-question