      Question

      3 men and 2 boys together can complete a work in 30

      days. 2 men and 6 boys can together complete half of the same work in 10 days. Find the time taken by 1 man and 1 boy together to complete 55% of the entire work.
      A 36 days Correct Answer Incorrect Answer
      B 40 days Correct Answer Incorrect Answer
      C 42 days Correct Answer Incorrect Answer
      D 48 days Correct Answer Incorrect Answer
      E 45 days Correct Answer Incorrect Answer

      Solution

      Let the efficiency of man and that of a boy be 'M' units/day and 'B' units/day respectively. Time taken by 2 men and 6 boys together to complete the entire work = 10 Γ— 2 = 20 days Then, total work = (3M + 2B) Γ— 30 = (2M + 6B) Γ— 20 Or, 90M + 60B = 40M + 120B Or, 50M = 60B So, M : B = 6 : 5 Let 'M' = '6x' and 'B' = '5x' Then, total work = (3Γ—6x + 2Γ—5x) Γ— 30 = (18x + 10x) Γ— 30 = '840x' units 55% of the total work = 840x Γ— 0.55 = '462x' units Time taken by 1 man and 1 boy together = 462x Γ· (6x + 5x) = 462/11 = 42 days