Question
'A' alone can do some work in 24 days, 'B' alone can do
the same work in 48 days. If they work on alternate days, starting with 'B', then the work will be finished in:Solution
Let the total work be 48 units {LCM (24 and 48)} So, efficiency of 'A' = 48 ÷ 24 = 2 units/day And efficiency of 'B' = 48 ÷ 48 = 1 unit/day Work done in every 2 days (B + A) = 1 + 2 = 3 units So, work done in 32 days by 'A' and 'B' = (32 ÷ 2) x 3 = 48 units Total time taken = 32 days
Which Five-Year Plan was based on the "P.C. Mahalanobis Model"?
What did Clement Attlee's announcement in the British Parliament proclaim?Â
Uniform Civil Code is related to which article?
Which individual has served as India’s Vice President for two separate terms?
How many members of the Rajya Sabha are nominated by the President of India?
What is the nature of the Rajya Sabha in the context of Indian Parliament?
Which of the following are the rights of the accused (of a criminal offence) as guaranteed by the Indian Constitution?
1. No person would be puni...
As per the recently notified Citizenship (Amendment) Rules, 2024 by the Government of India, which date is the cutoff for migrants to be eligible for In...
Who is the Ex-officio Chairman of India's Rajya Sabha?
Anti-Deflection law was described in