      Question

      A worker completes 30% of a job in 6 days. Assuming the

      same rate of work, in how many total days will he complete the whole job?
      A 18 days Correct Answer Incorrect Answer
      B 26 days Correct Answer Incorrect Answer
      C 20 days Correct Answer Incorrect Answer
      D 10 days Correct Answer Incorrect Answer

      Solution

      30% work → 6 days 1% work → 6 / 30 = 0.2 days 100% work → 100 × 0.2 = 20 days Answer: 20 days