ЁЯУв Too many exams? DonтАЩt know which one suits you best? Book Your Free Expert ЁЯСЙ call Now!

  • google app store apple app store
  • тЬЦ

      Question

      A worker completes 30% of a job in 6 days. Assuming the

      same rate of work, in how many total days will he complete the whole job?
      A 18 days Correct Answer Incorrect Answer
      B 26 days Correct Answer Incorrect Answer
      C 20 days Correct Answer Incorrect Answer
      D 10 days Correct Answer Incorrect Answer

      Solution

      30% work тЖТ 6 days 1% work тЖТ 6 / 30 = 0.2 days 100% work тЖТ 100 ├Ч 0.2 = 20 days Answer: 20 days

      Practice Next
      More Time and work Questions

      Relevant for Exams:

      ask-question