Question
'A' and 'B' together can complete the work in 15 days.
'B' alone can complete the work in 30 days. If C is 50% more efficient than A, find the time taken by 'C' alone to finish the work.Solution
Let the total work be 120 units Combined efficiency of 'A' and 'B' = (120/15) = 8 units/day Efficiency of 'B' alone = (120/30) = 4 units/day Efficiency of 'A' alone = 8 - 4 = 4 units/day Efficiency of 'C' = 4 X (3/2) = 6 units/day Time taken by 'C' alone to finish the work = 120 ÷ 6 = 20 days
Who won two awards at the International News Media Association Global Media Awards in London?
In which location was Jammu & Kashmir’s first Gen Z Post Office inaugurated?
- Which Indian Army regiment is representing the Indian side in Exercise DUSTLIK-VI?
What is the current Public Provident Fund (PPF) interest rate for January-March 2025, as per the unchanged small savings rates?
Consider the following statements about the banking sector's performance in FY24 and FY25:
1. Crisil forecasts a 14% credit growth for the bankin...
Nagaland celebrated its ______ Statehood Day on 1 December 2021.
Which microfinance company secured a $25 million loan from the US International Development Finance Corporation?Â
For the ‘Operation Vigilant Storm’ a defence military exercise USA and which other country has participated from 31st October to 4th November, 2022?...
The Centre for Economics and Business Research (CEBR) has predicted that India will become the third-largest economy in ________.
Who is the current Governor of the Reserve Bank of India (RBI) as per the latest ₹20 banknote issuance?