Question

    Raju and Raman can complete a piece of work in 12 days

    and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?
    A 13(2/3) days Correct Answer Incorrect Answer
    B 13 (1/2) days Correct Answer Incorrect Answer
    C 14 (2/3) days Correct Answer Incorrect Answer
    D 14 (1/3) days Correct Answer Incorrect Answer

    Solution

    ATQ,