      Question

      A does 4/5 of a piece of work in 20 days. He then calls

      in B and they finish the remaining work in 3 days. How long B alone will take to do whole work?
      A 37 1/2 days Correct Answer Incorrect Answer
      B 37 days Correct Answer Incorrect Answer
      C 40 days Correct Answer Incorrect Answer
      D 23 days Correct Answer Incorrect Answer
      E 27 days Correct Answer Incorrect Answer

      Solution

      Practice Next