Question
A can complete a work in 12 days and B in 18 days. They
work together for 6 days, then B leaves. How many total days to finish the work?Solution
ATQ, (A+B) rate = 1/12 + 1/18 = 5/36 Work in 6 days = 6×5/36 = 5/6 Remaining = 1/6 A’s rate = 1/12 Time = (1/6)/(1/12) = 2 days Total = 6 + 2 = 8 days
As per companies Act 2013, which of the following statements are correct?
1. A company shall not issue shares at a discount except sweat shares.<...
Conspiracy to wage war against the State_________.
As per the Bharatiya Nagarik Suraksha Sanhita, under what circumstance can a Court of Sessions take cognizance of an offence as a Court of Original jur...
What is the punishment for joining an unlawful assembly and continuing in it without armed weapons?
As per Section 24 of the Companies Act, 2013, the Power of Securities and Exchange Board (SEBI) is related to which of the following matters?
1. ...
Express offer means________________
All the facts except___________________ may be proved by oral evidence.
The quorum for a meeting of the Board of Directors of a company shall be ______________ and the participation of the directors by video conferencing or...
Which of the following is not a public document?
An application for initiating pre-packaged insolvency resolution process may be made in respect of ___________________ as laid down under the IBC