📢 Too many exams? Don’t know which one suits you best? Book Your Free Expert 👉 call Now!

  • google app store apple app store
  • ✖

      Question

      40 men are engaged to dig a 4 km long drainage channel.

      After working 12 days, only 1/2 of the work is done. Then 8 more men are employed. Find the number of days required to complete the remaining work.
      A 25 days Correct Answer Incorrect Answer
      B 4 days Correct Answer Incorrect Answer
      C 10 days Correct Answer Incorrect Answer
      D 12 days Correct Answer Incorrect Answer

      Solution

      ATQ, Let the number of days to complete the remaining work be x. (40 × 12) / (1/2 × 4) = 48x / (1/2 × 4) (40 × 12) / 2 = 48x / 2 240 = 24x x = 10 days

      Practice Next

      Relevant for Exams:

      ask-question