Question
A, B, and C together wrap up a task in 14 days. B and C together can finish it in (280/18) days, and C alone completes half in 14 days. Find the ratio of the efficiency of A to
B.
Solution
1/A + 1/B + 1/C = 1/14 C alone complete the whole work = 14 Γ 2 = 28 days B and C together = (280/18) days β rate = 18/280 = 9/140 1/A = 1/14 β 9/140 = (10 β 9)/140 = 1/140 1/B = 9/140 β 1/28 = (9 β 5)/140 = 4/140 = 1/35 A alone complete the work = 140 days B alone complete the work = 35 days Required ratio = (1/140) : (1/35) = 1 : 4
More Time and work Questions
- A and B can complete a piece of work in 12 days, B and C in 15 days and A and C in 20 days. In how many days can B alone complete the work?
- A can complete a work in 15 days. B takes 5 days less than A to complete the same work. In how many days can both of them together complete 60% of the work...
- 'Ajeet' has an efficiency that is 40% lower than 'Chirag's, where as 'Bittu' is 20% more efficient than 'Chirag'. The time difference between 'Bittu' and '...
- 'A' alone can do some work in 20 days, 'B' alone can do the same work in 30 days. If they work on alternate days, starting with 'B', then the work will be ...
- A and B can complete a work together in 30 days. If A alone can complete one-third of the work in βxβ days and remaining work is completed by B alone in 2x...
- A and B together can complete a piece of work in 12 days, while B and C can complete it in 15 days. A, B, and C together can complete the same work in 8 da...
- 50 men can complete a piece of work in 10 days. βxβ men started the work and after 5 days 60 more men joined them so that whole work was finished in the de...
- Vikram alone can finish some work in 20 days. Vikram and Varun completed the work together and earned Rs. 8,000 as wage. If Varun's wage share is Rs. 3,200...
- Ashish and Anil can do a piece of work in 20 days and 25 days respectively. Ashish completed 60% of the work. Find the time taken by Anil to complete the r...
- Working together, Amit and Pawan can finish a task in 22.5 days, and Pawan and Chirag can complete 60% of the same task in 14.4 days. Given that Amit is 12...