Question
Person 'X' can finish a task in 40 days while 'Y' can do it
in 50 days. How long will it take if both work together?Solution
ATQ,
Let the total work be 200 units (LCM of 40 and 50)
Efficiency of 'X' = 200 ÷ 40 = 5 units/day
Efficiency of 'Y' = 200 ÷ 50 = 4 units/day
Required time = 200 ÷ (5 + 4) = 22.22 days
Which of the following is NOT one of the biases in decision making?
Decision making process first requires identification of problem. Which of the following types of problems can be considered here?
How does a cost-benefit analysis contribute to selecting the best solution?
The pre-dispositioning theory of decision making was given by ___________
Which of the following is not a characteristic of decision making?
Which of the following is not a feature of Decision-making process?
Leaders use specific and different styles when contemplating decisions. One such style is the directive decision making style. Which of the following is...
Which of the following style of decision-making focuses on long term?
Which of the following best describes a decision tree?
Which of the following technique of decision making is a process in which a group of individuals generate and state ideas, but in which the rules prohib...