Question
Person 'X' can finish a task in 40 days while 'Y' can do it in 50 days. How long will it take if both work together?
Solution
ATQ,
Let the total work be 200 units (LCM of 40 and 50)
Efficiency of 'X' = 200 Γ· 40 = 5 units/day
Efficiency of 'Y' = 200 Γ· 50 = 4 units/day
Required time = 200 Γ· (5 + 4) = 22.22 days
More Time and work Questions
- A man can complete a task in 20 days, a woman can finish it in 30 days, and a boy can do the same task in 60 days. To complete the task in just 3 days, how...
- Rohan can do a piece of work in 30 days. Rohan with the help of Karan does the same piece of work in 20 days. If they are paid Rs 3696 for the work, then w...
- A and B individually can complete the work in 30 days and 45 days respectively. If the time taken by C alone to complete the work is 1.5 times the time tak...
- Abhijeet' is 50% less efficient than 'Vivek' and can achieve 25% of the sales target in 8 days.'Chirag' takes 4 days more than 'Vivek' to achieve the targe...
- Leela and Laila, working together, can complete a task in 18 days. Given that Laila is 125% more efficient than Leela, how long would it take for Laila to ...
- 55 men can complete a piece of work in 18 days. βxβ men started the work and after 9 days 64 more men joined them so that whole work was finished in the de...
- βAβ and βBβ alone can do a certain work in 30 days and 40 days, respectively. Both started the work together but after βxβ days βAβ left the work and the r...
- A alone can finish a piece of work in 15 days and B alone in 20 days. They work together for 4 days and then A leaves. In how many more days will B finish ...
- A fence is constructed using 900 wooden planks. βXβ alone can place 10 planks per minute, while βYβ alone can complete the fence in 100 minutes. βZβ, a cur...
- Priya completes 30% of a task in 9 days. Her efficiency is 50% greater than Meera's. How many days will it take for both Priya and Meera, working together,...