Question
Person 'X' can finish a task in 40 days while 'Y' can do it
in 50 days. How long will it take if both work together?Solution
ATQ,
Let the total work be 200 units (LCM of 40 and 50)
Efficiency of 'X' = 200 ÷ 40 = 5 units/day
Efficiency of 'Y' = 200 ÷ 50 = 4 units/day
Required time = 200 ÷ (5 + 4) = 22.22 days
Which of the following initiatives is associated with the Ministry of Cooperation?
Which example best represents the organized sector?
Pradhan Mantri Ujjwala Yojana is related with
Atal Bhujal Yojna is being implemented in how many states?
In the acronym CAGR, what does the letter ‘C’ stand for?
In which year was the Marginal Standing Facility (MSF) introduced by the Reserve Bank of India?
Consider the following statements about Cess:
I) Cess is not a permanent source of revenue for the government.
II) Cess can be imposed on ...
Which country's stock exchange is indexed by 'Bovespa'?
Who bears the main burden of an indirect tax?
Prevention of cruelty to animals is listed in which list of the Indian Constitution?