Question
R and S take 10 days and 15 days respectively to complete a
task alone. If they alternate work every day starting with R, how much time will it take to finish the job?Solution
ATQ,
Total work = 30 units (LCM of 10 and 15)
R’s efficiency = (30 ÷ 10) = 3 units/day
S’s efficiency = (30 ÷ 15) = 2 units/day
In 2 days = 3 + 2 = 5 units
Time = (30 ÷ 5) × 2 = 12 days
The position of how many alphabets will remain unchanged if each of the alphabets in the word ‘JURISDICTION’ is arranged in alphabetical order from ...
In each of the following questions which one of the answer figures shall complete the given question figure.
In each of the following questions which one of the answer figures shall complete the given question figure.
Study the given pattern carefully and select the number that can replace the question mark (?) in it.
Study the given pattern carefully and select the number that can replace the question mark [?] in it?
Select an appropriate figure from the given four options that would replace the question mark ‘?’ in the following figure series.
In each of the following questions which one of the answer figures shall complete the given question figure.
Select an appropriate figure from the four options that will come next in the following figure.
If 923 = 54, 781 = 56, 654 = 120, then 842 = ?
Select an appropriate figure from the four options that would complete the figure.