Question
R and S take 10 days and 15 days respectively to complete a task alone. If they alternate work every day starting with R, how much time will it take to finish the job?
More Time and work Questions
- P can do a piece of work in 20 days, Q can do the same piece of work in 24 days while R can do it in 30 days. They started working together but after 4 day...
- Komal and Seema individually can complete a task in ‘4a’ hours and ‘8a’ hours respectively. If they together can complete half of the work in 8 hours, then...
- 'X' and 'Y' together can complete the work in 16 days. 'Y' alone can complete the work in 24 days. If Z is 50% more efficient than X, find the time taken b...
- ‘A’ and ‘B’ can do a piece of work in 22 days and 25 days, respectively. If they started the work together and worked on it for 6 days, then find the time ...
- Gagan can do a piece of work in 14 days. Magan is 40% more efficient than Gagan. How many days will Magan and Gagan together complete the work?
- Two typists of different speeds can complete a typing job together in 6 minutes. If the 1st typist types alone for 4 minutes and then the 2nd typist types ...
- Ankit can complete a task in 16 days, while Bina alone can complete the same task in 24 days. Ankit starts the work alone and continues for 6 days. Then, B...
- A and B together can do a work in 12 days. If A can alone do the same work in 18 days, then in how many days B alone will do the same work?
- A man alone can do a work in 25 days. A woman can complete half of the same work in 20 days. In how many days can they complete 90% of the work together?
- (x + 9) laborers complete 45% of a task in 12 days working 5 hours/day. The rest is done by (x + 4) laborers in 18 days working 5 hours/day. Find x.