Question
R and S take 10 days and 15 days respectively to complete a
task alone. If they alternate work every day starting with R, how much time will it take to finish the job?Solution
ATQ,
Total work = 30 units (LCM of 10 and 15)
R’s efficiency = (30 ÷ 10) = 3 units/day
S’s efficiency = (30 ÷ 15) = 2 units/day
In 2 days = 3 + 2 = 5 units
Time = (30 Ă· 5) Ă— 2 = 12 days
The light and frequent rains of south west monsoon, soil permit sowing being done earlier than other soils called…………………..
...Tillage ______ thermal conductivity
Which of the following types of tea undergoes the least amount of processing, retaining a natural flavor profile?
Safflower oil is valued for its highÂ
Poor construction practices, inadequate maintenance, uncontrolled livestock access and cropping too close can all lead to
These mouthparts are adapted for piercing plant tissues and sucking up the cell contents. Insects feeds on a variety of plants by puncturing the plant c...
Physical condition of soil resulting from tillage is
When the activity of one gene is suppressed by the activity of a non-allelic gene, it is known as
Under conservation tillage how much of the field area is covered with the residue of crop?
Rice plants have a specific preference for the form of nitrogen they uptake. Which form is most efficiently absorbed by rice under submerged conditions,...