Question
R and S take 10 days and 15 days respectively to complete a
task alone. If they alternate work every day starting with R, how much time will it take to finish the job?Solution
ATQ,
Total work = 30 units (LCM of 10 and 15)
R’s efficiency = (30 ÷ 10) = 3 units/day
S’s efficiency = (30 ÷ 15) = 2 units/day
In 2 days = 3 + 2 = 5 units
Time = (30 ÷ 5) × 2 = 12 days
As per Economic Survey 2021-22, the Marginal Standing Facility rate remained unchanged at______?
The Sampoornata Abhiyan, a campaign launched by NITI Aayog, aims to:
The PM-PRANAM scheme was introduced to promote the use of biofertilizers and organic fertilizers, thereby reducing the reliance on chemical fertilizers....
As per the Economic Survey, what is the average annual growth rate of the Indian agriculture sector over the last five years at constant prices, and how...
The World Economic Outlook (WEO) 2024 projects global growth for 2024 and 2025 amidst a challenging economic environment. Services inflation has been a ...
The Pradhan Mantri Kisan Maandhan Yojana (PM-KMY) is an old-age pension scheme aimed at providing financial support to small and marginal farmers. Howev...
In economic terminology, Isoquants denote
In economic terminology, to assess the relationship between complements a battery and a car you should find out the _________ that generally is ________...
As per the SDG India Index 2023-24 , significant progress has been made in various Sustainable Development Goals (SDGs) through targeted interventions a...
In terms of economics, demand would be inelastic when