Question
Person A can complete 25% of a job in 4 days. Person B is
20% less efficient than Person A. How many days will it take for both A and B, working together, to complete 90% of the job?Solution
‘A’ can complete whole work alone in 4/0.25 = 16 days
‘B’ can complete the whole work in = 16/0.80 = 20 days
Let the total work = 80 units
Efficiency of ‘A’ = 80/16 = 5 units/day
Efficiency of ‘B’ = 80/20 = 4 units/day
Required time taken = 0.9 × 80/(5 + 4) = 8 days
The phenomenon slickenside is found in
The action to remove food from the market at any stage of the food chain, including that possessed by consumers is called:
A microbial process in the nitrogen cycle that involves the reduction of nitrate (NO ₃⁻ ) and nitrite (NO ₂⁻ ) in soil or water to gaseous nitro...
Which sub-scheme of Prampargat Krishi Vikas Yojna (PKVY) is associated with the promotion of natural farming?
A burnt or caramel flavor in milk is caused by:
Bacteria responsible for oxidizing NO2-, NO3-in soils is __ ?
Setting a price below that of the competition is called
How many kcal/g do organic acids present in fruits and vegetables provide?
Global rank of India in terms of Vegetable and Fruit Production?
Which of the following ameliorate is cost effective and easily available for the reclamation of sodic soil?