Question
βPβ alone can complete a work in 25 days while
βPβ and βQβ together can complete the whole work in 15 days. Find the time taken by βQβ alone to complete the whole work.Solution
Let total work = 150 units (LCM of 25 and 15)
Amount of work completed by βPβ alone in one day = 150/25 = 6 units
Amount of work completed by βPβ and βQβ together in one day = 150/15 = 10 units
Amount of work completed by βQβ alone in one day = 10 β 6 = 4 units
Desired time taken by βQβ alone to complete the work = 150/4 = 37.5 days
Calculate the volume ofΒ pendimethalin (30% EC) for 8000 mΒ² Β wheat field, if application rate is 1 kg a.i./ha.
An example for a plant hormone isΒ
First interspecific cross was made by which of the following Scientist?
The term pegging is concerned to which crop?
Wind direction is measured as β
In which year was the system of 'minimum support prices' (MSP) initiated in India to ensure farmers receive remunerative prices and promote the use of H...
Linkage drag is the phenomenon in which-
Which of the following is ephemeral weed?
Value of correlation coefficient lies between
Bacterial artificial chromosome may be used for the construction of: