Question
βPβ alone can complete a work in 25 days while
βPβ and βQβ together can complete the whole work in 15 days. Find the time taken by βQβ alone to complete the whole work.Solution
Let total work = 150 units (LCM of 25 and 15)
Amount of work completed by βPβ alone in one day = 150/25 = 6 units
Amount of work completed by βPβ and βQβ together in one day = 150/15 = 10 units
Amount of work completed by βQβ alone in one day = 10 β 6 = 4 units
Desired time taken by βQβ alone to complete the work = 150/4 = 37.5 days
In how much time will a train running with a speed of 72 km/hr cross the second train?
I. The length of the two trains is 80 metres and 100 metre...
What is the monthly salary of Amit?
Statement I. Amit spends one-third of his salary on household expenses, one –fourth on travel expenses...
The question consists of two statements numbered βI and IIβ given below it. You have to decide whether the data provided in the statements are suffi...
How many days will it take for 4 boys and 10 girls to complete the task?
Statement I: A group of 5 boys and 8 girls can finish the task in 12 da...
Suppose train P crosses train Q in 55 sec when travelling in same direction then, Determine the length of train P.
Statement I : Speed of train ...
What was the percentage of discount offered?
I) Profit earned by selling the article for Rs. 324 after giving a discount was Rs. 24.
II) H...
In a company there are supervisors and clerks. The total monthly salary of the employees is Rs. 10.5 Lakh. What is the total number of employees in tha...
Which one of the following is correct in respect of the statement given below?
Statement 1: 210Β is the smallest natural number having...
What is the speed of a boat in still water?
Statement I: Β The boat covers a distance of 120km in 5 hours while running upstream.
Statem...
How much time will Bus A take to cross Bus B (from the moment they meet) running in opposite directions (towards each other)?
Statement I: The ...