Question
βPβ alone can complete a work in 25 days while
βPβ and βQβ together can complete the whole work in 15 days. Find the time taken by βQβ alone to complete the whole work.Solution
Let total work = 150 units (LCM of 25 and 15)
Amount of work completed by βPβ alone in one day = 150/25 = 6 units
Amount of work completed by βPβ and βQβ together in one day = 150/15 = 10 units
Amount of work completed by βQβ alone in one day = 10 β 6 = 4 units
Desired time taken by βQβ alone to complete the work = 150/4 = 37.5 days
x men can finish a work in y days. 0.9x women can finish 1/3rd of the same work in (y - 8) days. If 0.8x women can complete 1/3rd work in 36 days. Find ...
Chacha and Bhatija can complete a work in 48 days. In how many days Chacha alone does the 2/3rd of the total work if they start working toget...
40 men can complete a piece of work in 24 days. All of them started the work together, after 6 days how much more men will be required to complete the s...
Sita is 50% more efficient than Simran. Working together, they finish the work in 24 days. How long will Sita take to complete the work alone?
P can do a piece of work in 15 days, Q can complete double the work in 30 days and R can do the work in 25 days. If all of them together earn Rs. 2600, ...
Carol, Bruce, and Peter can decorate a venue in 7, 14, and 21 days respectively. If they start working together, but Carol leaves 3 days before completi...
'x' men can complete a work in 60 days. If there had been 20 more men, the work would have been completed in 30 days. Find the value of 'x'.
A can count 100 eggs in 4 minutes while B can count the same number of eggs in 5 minutes. How much time will be required if they work together to count ...
2 men and 3 boys can do a piece of work in 405 days while 3 men and 2 boys can do the same work in 324 days. In how many days can 5 men and 5 boys do th...
X men can complete the piece of work in 36 days and (X + 35) men can complete the same work in 14 days less than that of days taken by X men. Find the v...