Question
‘P’ alone can complete a work in 25 days while
‘P’ and ‘Q’ together can complete the whole work in 15 days. Find the time taken by ‘Q’ alone to complete the whole work.Solution
Let total work = 150 units (LCM of 25 and 15)
Amount of work completed by ‘P’ alone in one day = 150/25 = 6 units
Amount of work completed by ‘P’ and ‘Q’ together in one day = 150/15 = 10 units
Amount of work completed by ‘Q’ alone in one day = 10 − 6 = 4 units
Desired time taken by ‘Q’ alone to complete the work = 150/4 = 37.5 days
The 2nd phase of 36 ‘Saansad Khel Mahakumbh 2022-23’ has been inaugurated in which district of the state Uttar Pradesh?
Three statements are followed by four conclusions numbered I, II, III, and IV. You have to consider these statements to be true, even if they seem at va...
On which date the currency system in India is converted into the decimal system?
Where in India the first ever Underwater Metro Train to be set up in which city and will be operated from the year 2023?
Which of the following statements is/are NOT TRUE with respect to the PM Vishwakarma Scheme ?
I.The Reserve Bank of India (RBI) has decided to ex...
Mai Bhi Digital Campiagn is being run for ______?
Which of the following is a popular women’s Empowerment programme in India?
Who is the brand ambassador of Arogya Setu app?
मूल अधिकारों से संबंधित मामला निम्नलिखित में से कौनसा ह...
The ONGC Videsh Limited has recently announced an oil discovery in which country ?