Question

‘P’ alone can complete a work in 25 days while ‘P’ and ‘Q’ together can complete the whole work in 15 days. Find the time taken by ‘Q’ alone to complete the whole work.

A 20 days
B 37.5 days
C 35 days
D 45 days