Question
A group of 'x' men can finish a job in 46 days. If 8
additional men had joined the group, they could have completed the same job 16 days earlier. Assuming all men work at the same efficiency level, determine the value of 'x'.Solution
Let efficiency of each man = ‘M’ units/day ATQ, (x × M × 46) = {(x + 8) × M × (46 – 16)} Or, 46x = 30x + 240 Or, 16x = 240 Or, x = (240/16) = 15
The average of three numbers a, b and c is 2 more than c. The average of a and b is 48. If d is 10 less than c, then the average of c and d is:
If the sum of three numbers is zero, then which of the options below will always be equal to the value of the sum of the cubes of those numbers?
If  x = 19 , find x 5 - 20  x 4 + 20  x 3 - 20x 2 + 20x  - 20 = ?
Given that x8-34x4+1=0, x>0. What is the value of (x3+ x-3)?

If x2a = y2b =z2c ≠ 0 and x2 = yz, then the value of (ab + bc + ca) /bc is :
when x =4 and y =-6 then find the value of 27x³ +58x²y +31xy² +8y³?
Given that x = 80, y = -35 and z = -45, Determine the value of [(x³ + y³ + z³)/10³]
22% of ‘x’ is equal to 66% of ‘y’, then find the value of x: y.
If, 4x + y = 10, and 2xy = 8, and 4x > y, then find the value of 64x³ – y³.