Question
Aman and Priya can paint a house in 20 days. Priya and
Rina can paint the same house in 30 days, while Aman and Rina can paint it in 40 days. How many days will it take for all three of them to paint the house together?Solution
(Aman +Priya)        (Priya +Rina)(        (Aman+Rina) 20                         30                         40                              120(total work) 6                           4                           3       -Efficiency. Total Efficiency of Aman Priya and Rina – 2(Aman + Priya + Rina) =6+4+3=13 (Aman + Priya + Rina) =13/2=6.5 And now together to clean the apartment=120/6.5 =1200/65 =240/13 =18(6/13)
A and B together can finish a work in 10 days. If A alone can finish it in 25 days, in how many days can B alone finish it?
A man, a woman and a boy can do a work in 4, 8, 16 days respectively. How many boys were required with 1 man and 1 woman to complete the same work in 1/...
A man is thrice as fast as a women and a woman is twice as fast as a boy. If all of them can do a work in 18 days. than a boy can do the work in?
x men can finish a work in y days. 0.9x women can finish 1/3rd of the same work in (y - 8) days. If 0.8x women can complete 1/3rd work in 36 days. Find ...
'Ramesh' can complete a work in 40 days. He started the work and left after 24 days from starting. The remaining work was done by 'Suresh' in 30 days. F...
A and B finish a job together in 36 days, while B and C together finish it in 48 days. The trio completes 75% of the job in 18 days. In how many days wi...
There is enough food in a camp to last for 50 days if each of the 40 soldiers present at the camp eat 2 times a day. After 20 days, 40 more soldiers jo...
- Suppose D, E and F can do a piece of work individually in 18, 27 and 36 days respectively. If they combine and work for 4 days, what percentage of work wou...
- A builder employed 12 workers to complete a job in 18 days. But after 8 days, 4 workers quit. How many more days will be required to complete the remaining...
Twenty laborers can complete a piece of work in 12 days. If 20 laborers started working and after 3 more days, additional laborers joined to complete th...