Question
A contractor hired 40 workers to complete a work in 100 days. After 70 days, it was found that only 2/5th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.
More Time and work Questions
- A man, a woman and a girl can together complete a piece of work in 60 days. If 10 men can do it in 16 days and 8 girls can finish it in 30 days, how long w...
- ‘P’ and ‘Q’ can complete a task together in 24 days. If ‘P’ alone can do it in 40 days, find the number of days ‘Q’ alone will take to finish the task.
- A started a work such that he can complete the whole work in 30 hours. After working for 10 hours, he worked with the rate such that the whole work can be ...
- If A can complete a job in 15 days and B can complete the same job in 10 days, and they work together for 4 days before A leaves. How many more days will B...
- Two individuals, P and Q, can complete a task in (x + 6) days and (x + 3) days, respectively. Another individual, S, is capable of completing 25% of the sa...
- 'M' alone finishes a project in 30 days. 'M' and 'N' together can complete the same project in 16(2/3) days. How many days would 'N' need to do the project...
- A and B together can complete a work in 12 days, B and C together in 16 days, and A and C together in 24 days. All three start working together. After 3 da...
- A' can finish a job in 24 days, while 'B' is 25% less efficient than 'A.' If they take turns working, beginning with 'A,' how many days will it take for th...
- If Riya takes three times the time that Mahi takes or four times the time that Neha takes to finish a task, and all three working together can complete it ...
- A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt