Question
A contractor hired 40 workers to complete a work in 100
days. After 70 days, it was found that only 2/5th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Let 'n' more workers joined after 70 days and let total work be 5W units. Using (men X days) ÷ work = constant Simplifying,
Therefore, 100 extra workers are needed so that work gets completed on time.
For 3x² − 10x − 8 = 0, find (1/α + 1/β).
In the question, two equations I and II are given. You have to solve both the equations to establish the correct relation between x and y.
I. 3x<...
I. 2x2 - 9 x + 9 = 0Â
II. 2y2 - 7 y + 3 = 0
I. 8x² - 74x + 165 = 0
II. 15y² - 38y + 24 = 0
I. 3x2 - 16x - 12 = 0
II. 2y2 + 11y + 9 = 0
In the question, two equations I and II are given. You have to solve both the equations to establish the correct relation between 'p' and 'q' and choose...
For what values of k does the equation x² – (k+1)x + k = 0 have two distinct real roots, both greater than 1?
l. x2 - 16x + 64 = 0
II. y2Â = 64
I. 66x² - 49x + 9 = 0
II. 46y² - 37y - 30 = 0
I. 3p² - 17p + 22 = 0
II. 5q² - 21q + 22 = 0