Question
A contractor hired 40 workers to complete a work in 100
days. After 70 days, it was found that only 2/5th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.Solution
ATQ, Let 'n' more workers joined after 70 days and let total work be 5W units. Using (men X days) ÷ work = constant Simplifying,
Therefore, 100 extra workers are needed so that work gets completed on time.
The coefficient of regression of Y on X is byx = 1.2 , If A = (X-300)/4 and C = (Y-500)/6 find bCA
Consider a Keynesian Cross Model with following features, Consumption Function: C= C0 + b (Y – T) Â
Tax Function: T = T0 + tY Â
I...
Suppose we regress the dependent variable y on four independent variables x1, x2, x3, and x4. After running the regression on n = 16 observatio...
Which of the following defines ambient standards in an environmental policy
A firm should increase investment when :
Which of the following statements are correct about trilemma in monetary policy
A. It is related to closed economy model.
B. It involves...
Which of the following statements are correct about trilemma in monetary policy
A. It is related to closed economy model.
B. It involves...
Which of the following defines ambient standards in an environmental policy
Consider a Keynesian Cross Model with following features, Consumption Function: C= C0 + b (Y – T)
Tax Function: T = T0 + tY
Income...
Two people enter a bus. Two adjacent cramped seats are free. Each person must decide whether to sit or stand. Sitting alone is more comfortable than sit...