πŸ“’ Too many exams? Don’t know which one suits you best? Book Your Free Expert πŸ‘‰ call Now!

  • google app store apple app store
  • βœ–

      Question

      A contractor hired 40 workers to complete a work in 100

      days. After 70 days, it was found that only 2/5th of the work was completed. Find the number of extra workers needed to be hired, so that the work gets completed on time.
      A 100 Correct Answer Incorrect Answer
      B 250 Correct Answer Incorrect Answer
      C 200 Correct Answer Incorrect Answer
      D 220 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      ATQ, Let 'n' more workers joined after 70 days and let total work be 5W units. Using (men X days) Γ· work = constant Simplifying, Therefore, 100 extra workers are needed so that work gets completed on time.

      Practice Next
      ask-question