Question

Efficiency of 'D' is 80% more than that of 'E' and 25% less than that of 'F'. They start working together, but 'E' leaves after 3 days, and the remaining work is completed by 'D' and 'F' together in 4 days. How long would it take for 'D' to complete the entire work alone?

A 18 days
B 25 days
C 35 days
D 65 days
E none of these