Anil, Bheem and Tina can complete a work separately in 12, 18 and 24 days respectively. They started together but Tina left after 4 days of start and Anil left 3 days before the completion of the work then,In how many days will the work will complete?

A 6.8 days
B 7.8 days
C 7 days
D 7.2 days
E none of these