Anil, Bheem and Tina can complete a work separately in
12, 18 and 24 days respectively. They started together but Tina left after 4 days of start and Anil left 3 days before the completion of the work then,In how many days will the work will complete?Solution
ATQ we can say that, Let the total work be(L.C.M of 12,18 and 24) = 72 units. Anil’s one day work = 72/12 = 6 units Bheem’s one day work = 72/18 = 4 units Tinku’s one day work = 72/24 = 3 units (Anil + Bheem + Tinku)’s 4 days work = ((6 x 4) + (4 x 4)+ (3 x 4)) = = 24 + 16 + 12 = 52 units Anil’s 3 days work = 18 units Number of days for which (Anil + Bheem) worked together = 72−52+(18/10) = 3.8 days Hence, required number of days = 7.8 days
Who has been elected as the non – executive chairman of India bulls Housing Finance in August 2020?
Mohenjodaro site of Harappan civilisation is situated on the bank of which river?
What was India's rank in the Asia-Pacific Personalised Health Index released by the Economist Intelligence Unit in January 2021?
Competition Act 2002 is the replacement of which of the following Act?
Which commission recommended reforms in Centre-State financial relations?
Who is the captain of West Indies ODI and T20 cricket team?
Who is the nodal agency for Saubhagya Scheme?
_____________ is one of the most important festivals of Kamakhya temple of Guwahati. It is held every year during the monsoon (mid-June) season, when th...
When was the Hindustan Republican Association formed?
Ibrahim Lodi was defeated by ________ in the battle of Panipat.