Question
40 men can complete a piece of work in 48 days. ‘x’
men started the work and after 33 days 64 more men joined them so that whole work was finished in the desired time. Find the value of ‘x’Solution
Total work = 40 × 48 = 1920 units According to question; 33 × x + 15 × (x + 64) = 1920 Or, 33x + 15x + 960 = 1920 Or, 48x = 960 Or, x = 20
Sales = ₹200 lakhs, Variable cost = ₹120 lakhs, Fixed cost = ₹30 lakhs
Interest = ₹10 lakhs
Calculate (i) Operating Leverage and (...
A high Inventory Turnover Ratio indicates:
Which of the following is a useful liquidity metric for short-term creditors?
A firm evaluates two projects with identical expected cash flows, but Project A has higher variability. If the firm is risk-averse, what would be its de...
A firm uses 70% debt financing at 10% interest. Its ROE rises despite flat operating profits. What explains this phenomenon?
A firm’s gross profit is ₹50 lakh, sales are ₹2 crore. What is its gross profit margin?
A company refinances a short-term loan (due in 4 months) after the balance sheet date but before the financial statements are authorised. Management arg...
Which of the following formulae correctly calculates the Operating Profit Margin?
XYZ Ltd. is a medium-sized manufacturing company. Its summarized Balance Sheet and additional financial information for the year ended 31st March 2024 a...
While preparing cash flow statement, an entity (other than a financial institution) should disclose the dividends received from its investment in shares...