Question

    A man, a woman and a boy can do a work in 3, 2, 6 days

    respectively. How many children were required with 1 man and 1 woman to complete the same work in 1/2 day?
    A 6 Correct Answer Incorrect Answer
    B 3 Correct Answer Incorrect Answer
    C 8 Correct Answer Incorrect Answer
    D 7 Correct Answer Incorrect Answer

    Solution

    Work done by a man in (1 )/(2 ) days = (1 )/(6 ) part Work done by a woman in (1 )/(2 ) days = (1 )/(4 ) part Work done by a boy in (1 )/(2 ) days = (1 )/(12 ) part Let one man and one woman together can do a piece of work in (1 )/(2 ) days = No. of x children required According to the question, (1 )/(6 ) + (1 )/(4 ) + (x )/(12 ) = 1 (2 + 3 + x )/(12 ) = 1 5 + x = 12 x = 12 – 5 = 7 Hence, 7 boys will be required.