Question
A man, a woman and a boy can do a work in 3, 2, 6 days
respectively. How many children were required with 1 man and 1 woman to complete the same work in 1/2 day?Solution
Work done by a man in (1 )/(2 ) days = (1 )/(6 ) part Work done by a woman in (1 )/(2 ) days = (1 )/(4 ) part Work done by a boy in (1 )/(2 ) days = (1 )/(12 ) part Let one man and one woman together can do a piece of work in (1 )/(2 ) days = No. of x children required According to the question, (1 )/(6 ) + (1 )/(4 ) + (x )/(12 ) = 1 (2 + 3 + x )/(12 ) = 1 5 + x = 12 x = 12 – 5 = 7 Hence, 7 boys will be required.
If Sanjay and the person who have Red interchange their visiting days then how many persons visits after the person who likes BLACK colour?
As many persons senior to Z is same as junior to _____.
Who among the following live on the even floor?
I. N
II. Z
III. B
How many such pair(s) of letters are in the word “PROGRESS” which has as many letters between them (both forward and backward) as in the English alp...
Who purchased the bungalow 18 years ago?
Which of the following statements is correct?
How many persons' anniversaries are falling between Aditya's and Ashok's?
On which floor does the person live who likes Shreya ghoshal?
Which of the following statements is correct?
How many persons live above K?