span >50 people type 500 booklets in 30 days. In how many days will 30 people type 150 such booklets?
More Time and work Questions
- Ram can do a piece of work in 12 days and Shyam can do the same work in 20 days. They both started work together, Ram left 4 days before the completion of ...
- The time taken by P to complete a task is half of the time taken by Q. Q and R working together finish the task in 20 days, while P and R take 15 days. How...
- Anil and Ashish receive Rs.2000 for work of 8 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
- X can finish a task in 20 days, while Y can do it in 25 days. If Z needs 1.2 times the time taken by X and Y together, find the number of days Z will take ...
- A and C together can paint a wall in 18 days. If C takes 36 days to do it alone, and C works for 27 days after A leaves the job, what is the percentage of ...
- A alone can complete a piece of work in 15 days, while B alone can complete it in 20 days. They start the work together, and after some days A leaves. B co...
- Sonia and Riya decided to complete a piece of work together. Sonia is capable of doing 9 units of work per day, whereas Riya can finish the complete task a...
- Ananya and Riya can complete a task in 20 hours and 40 hours respectively. Ananya works alone for 10 hours and then Riya finishes the remaining task. How l...
- A can complete 5/6 of a work in 15 days and B can complete 2/3 of work in 8 days. In how many days both A and B together can complete the work?
- ‘A’ can do a piece of work in 10 days. ‘B’ can do 80% of the same work in 20 days. If they work together for the entire time and get paid Rs.1400, then fin...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt