132 unit of work can be completed by P alone in 22 days.
P started working alone and joined by Q after 10 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (132/22) = 6 units/day According to question: 6 Γ 10 + (6 + x) Γ 6 = 132 Or, 60 + 36 + 6x = 132 Or, 6x = 132 β 96 Or, 6x = 36 Or, x = 6 Number of days taken by Q to complete the work alone = (132/6) = 22 days
The Global IndiaAI Summit 2024, organized by the Ministry of Electronics and Information Technology, aims to:
What is the percentage decline in the annual per capita availability of water in India?
Which of the following is not the parameters of niti aayog’saspirational district index?
What is the main goal of the Indo-Pacific Economic Framework for Prosperity (IPEF)?
Which of the following items are considered as One-District One-Product (ODOP) under PM FME Scheme?
(I)- Perishable agri-produce
(II)- Cer...
The Deen Dayal Upadhyaya Grameen Kaushalya Yojana (DDU-GKY) specifically aims to:
Which international agreement regulates the production and consumption of ozone-depleting substances (ODS)?
Which category under the PM Mudra Yojana allows for the highest loan amount, and what is the maximum loan limit?
Under the PM-KUSUM Scheme, Component-B supports installation of:
Which of the following States have achieved the target number of registrations on e-Shram Portal?
I- Odisha
II- Uttar Pradesh
III- ...