Question
132 unit of work can be completed by P alone in 22 days.
P started working alone and joined by Q after 10 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (132/22) = 6 units/day According to question: 6 × 10 + (6 + x) × 6 = 132 Or, 60 + 36 + 6x = 132 Or, 6x = 132 – 96 Or, 6x = 36 Or, x = 6 Number of days taken by Q to complete the work alone = (132/6) = 22 days
Which country will now allow visas for tourists after lifting ban on cinema theatres
Which region in the Philippines was impacted by Typhoon Krathon in September 2024?
Chandigarh's famous mango festival is been celebrated in the month of June and what is the fixed venue of it?
The works of Tulsidas includes:
a) Granthavali
b) Krishnavali
c) Ratna Ramayan
d) Ramcharitmanas
Who was named the ICC Men’s Player of the Month for March 2025?
Match List-I with List-II and select the correct answer using the code given below:
Jim Corbett National Park, the oldest national park in India, is situated in which state -Â
Shares of large, medium and small caps are traded at BSE Indonext
World Wetlands Day is observed yearly?
Who is the author of the book 'Fire on the Ganges: Life Among the Dead in Banaras,' released by HarperCollins?