132 unit of work can be completed by P alone in 22 days.
P started working alone and joined by Q after 10 days such that they completed the remaining work in 6 days. Find the number of days taken by Q to complete the whole work alone.Solution
Let the efficiency of Q = x units/day Efficiency of P = (132/22) = 6 units/day According to question: 6 × 10 + (6 + x) × 6 = 132 Or, 60 + 36 + 6x = 132 Or, 6x = 132 – 96 Or, 6x = 36 Or, x = 6 Number of days taken by Q to complete the work alone = (132/6) = 22 days
The _______ edition of Coastal Defense Exercise ‘Sea Vigil’ 2022 was conducted by Indian Navy and Indian Coast Guard.
Which city in Uttar Pradesh is known for its Chikankari embroidery?
On the basis of the source of origin, the rivers of Uttar Pradesh are divided into ............... .
Name the area of Uttar Pradesh which is famous for terracatta craft.
What is the base year for the Reserve Bank of India - Digital Payments Index (RBI-DPI)?
Which of the following banks has been recognized as the ‘World Best SME Bank’ for the second time by Euromoney?
In which zone is Hubli railway station in?
In which state of India the Kangra Valley Festival is recently being inaugurated?
Which component of the environment is an example of an abiotic factor?
Which Indian state is home to the Rihand Dam?