Question
A and B together can do a work in 6 days. If A can alone
do the same work in 9 days, then in how many days B alone will do the same work?Solution
Total work = Number of days × 1 day’s work (efficiency) Total work = LCM (6, 9) = 18 unit 1 day’s work of (A+B) = 18/6 = 3 unit 1 day’s work of A = 18/9 = 2 unit 1 day’s work of B = 3 - 2 = 1 unit Now, Time taken by B to completed the work = 18/1 = 18 days
Which two Indian states will be connected by India's first bullet train?
What is the primary objective of ISRO’s SpaDeX mission?
What is the major announcement made by Tamil Nadu Chief Minister M.K. Stalin regarding minority educational institutions?
What is the rank of India in Aviation safety ranking by ICAO?
The SCORES platform, launched in_________ , was an initiative by SEBI to provide a facilitative platform for investors to file their grievances against ...
The Gujarat government has signed an MoU with a proposed investment of Rs 2,000 crore by the financial year 2030 (FY30) with a fintech company that will...
Which initiative is DPIIT launching under the Startup India program to boost India's startup ecosystem?
_________ has become the only state in the country to achieve 90.5% of immunization apart from the successful vaccination against Covid-19 infection und...
First seminar of Agni Tattva Campaign under LiFE Mission was organized in _____.
Which state announced the 'Sushma Swaraj Award' for women for their significant contribution or achievements in different walks of life in national and ...