      Question

      10 man can make a wall in 5 days. How many men

      required to complete the same work in 10 days ?
      A 6 Correct Answer Incorrect Answer
      B 5 Correct Answer Incorrect Answer
      C 15 Correct Answer Incorrect Answer
      D 10 Correct Answer Incorrect Answer
      E None of these Correct Answer Incorrect Answer

      Solution

      Given, M1 = 10, D1 = 5, M2 = ? and D2 = 10
      From M1D1 = M2D2
      ⇒ 10 x 5 = M2 x 10
      ⇒ M2 = (10 x 5)/10
      ∴ M2 = 5