Question
A and B together can complete a piece of work in 50 days
while B and C together can complete the same work in 60 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. valueSolution
Time taken by A, B and C together to complete the whole work = 26.4/0.80 = 33 days Let total amount of work = 3300 (LCM of 50, 60 and 33) Efficiency of (A + B) = 3300/50 = 66 units per day Efficiency of (B + C) = 3300/60 = 55 units per day Efficiency of (A + B + C) = 3300/33 = 100 units per day Efficiency of A = 100 – 55 = 45 units per day Efficiency of C = 100 – 66 = 34 units per day Desired time = 3300/79 = 41.7 days = 42 days
With reference to the office of the Attorney General of India, Which of the following statements is/are correct?
I. He is the highest law offic...
Saikhom Mirabai Chanu is an _______ .
 Which of the following referred to as ‘paper taxes’?
I.             Weather tax
II.           Gift tax
How many planets are terrestrial planets?
Who heads the Inter-Ministerial Committee on Investment in Critical and Foreign Technologies (IMICF)?
Which symbiotic bacterium is responsible for nitrogen fixation?
What is the maximum application amount that individuals can utilize UPI for, as per the guidelines issued by SEBI for public issues of equity shares and...
Who was the first woman to receive the Arjuna award for Hockey?
Consider the following statement about the peace agreement done by Government of India in December 2023:Â
1. It was signed between United Nation...
RBI has launched the Payments Vision document 2025 with the theme of: