Question
A and B can do a job in 20 days and 30 days,
respectively. A and B work together for 5 days, and then A leaves. After how many more days will B complete the remaining work?Solution
Work done by A per day = 1/20, Work done by B per day = 1/30. In 5 days, work done by A and B together = 5 × (1/20 + 1/30) = 5 × (3/60 + 2/60) = 5 × 5/60 = 25/60 = 5/12 of the work. Remaining work = 1 - 5/12 = 7/12 of the work. Now, B will complete the remaining work alone. Work done by B per day = 1/30. Time taken by B to complete the remaining work = (7/12) ÷ (1/30) = (7/12) × 30 = 17.5 days. Correct option: c
India participating with which countryin the military exercise 'Nomadic Elephant- 2023'?
Which major infrastructure project worth ₹685 crore was virtually inaugurated by Prime Minister Narendra Modi in Madhya Pradesh on Swachhta Diwas 2024?
Payment Lounge, introduced by Aditya Birla Capital Digital Limited, is described as an omni-channel platform. What does "omni-channel" mean in this cont...
- Which Indian Army regiment is representing the Indian side in Exercise DUSTLIK-VI?
On which river is the Nagarjuna Sagar Dam constructed?Â
__________ second highest military award for gallantry during wartime.
What was the total prize pool for the Women’s T20 World Cup 2024, as announced by the ICC?
Which of the following statements about India's startup ecosystem and the projected rise in unicorns in FY25 is correct?
The 'One Nation, One Election' plan requires constitutional amendments, particularly to which of the following Articles?
Which of the following frameworks offers greater flexibility for passively managed mutual fund schemes?