Question
A and B can do a job in 20 days and 30 days,
respectively. A and B work together for 5 days, and then A leaves. After how many more days will B complete the remaining work?Solution
Work done by A per day = 1/20, Work done by B per day = 1/30. In 5 days, work done by A and B together = 5 × (1/20 + 1/30) = 5 × (3/60 + 2/60) = 5 × 5/60 = 25/60 = 5/12 of the work. Remaining work = 1 - 5/12 = 7/12 of the work. Now, B will complete the remaining work alone. Work done by B per day = 1/30. Time taken by B to complete the remaining work = (7/12) ÷ (1/30) = (7/12) × 30 = 17.5 days. Correct option: c
How is O related to N’s brother?
There are seven members (R, S, T, U, W, Y and V) in a family. V is the daughter of T’s brother. Y is the father of R. W is the mother of Y. U is fathe...
How was A related to E?
Answer the questions based on the information given below.
There are eight family members L, M, N, O, P, Q, R and S having two married couples ...
Answer the questions based on the information given below.
Nine persons G, K, M, F, H, J, I, N and L are there in the family of three generat...
How is M related to J?
Which of the following statements is/are definitely correct?
How is C related to E? Â
If brother of L is the husband of H’s son’s sister, then which of the following expression is true?
How many male members are there in the family?
...