Question

    A and B together can complete a piece of

    work in 44 days while B and C together can complete the same work in 55 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. value
    A 51 days Correct Answer Incorrect Answer
    B 57 days Correct Answer Incorrect Answer
    C 50 days Correct Answer Incorrect Answer
    D 44 days Correct Answer Incorrect Answer
    E 60 days Correct Answer Incorrect Answer

    Solution

    Time taken by A, B and C together to complete the whole work = 26.4/0.80 = 33 days
    Let total amount of work = 660 (LCM of 44, 55 and 33)
    Efficiency of (A + B) = 660/44 = 15 units per day
    Efficiency of (B + C) = 660/55 = 12 units per day
    Efficiency of (A + B + C) = 660/33 = 20 units per day
    Efficiency of A = 20 – 12 = 8 units per day
    Efficiency of C = 20 – 15 = 5 units per day
    Desired time = 660/13 = 50.7 days = 51 days