Question
span >A and B together can complete a piece of work in 44 days while B and C together can complete the same work in 55 days. All of three together can complete 80% of the whole work in 26.4 days then find the time taken by A and C together to complete the whole work. Note: You have to find approx. value
More Time and work Questions
- A alone can complete a piece of work in 18 days and B alone can do it in 24 days. They work together for 6 days, after which A leaves. In how many more day...
- Before 'A' joined the team, 'S' and 'V' were alternating days to complete a project. In the final four days, 'A', 'S', and 'V' all worked together to finis...
- Anand is capable of finishing a task in 36 days when working solo. Akash, being 40% more efficient than Anand, can accomplish tasks quicker. Calculate how ...
- A buffalo alone can plough field ‘A’ in 40 days. A Bull alone can plough the field ‘A’ in 80 days. Find the number of days taken by 3 bulls and 1 buffalo t...
- A task can be finished by 'P' and 'Q' alone in 10 days and 5 days, respectively. 'P' and 'Q' started the task together and after 3 days, 'P' was replaced b...
- ‘M’ alone can complete a work in 18 days. ‘N’ is 50% as efficient as ‘M’. How long will they take to complete the work together?
- 30 workers putting in 8 hours a day finish a task in 10 days. How many days will it take for 20 workers working 12 hours daily to finish the same task?
- Akash can finish a task alone in 24 days, while Akash and Bittu working together can complete the same task in 14 days. If Bittu starts the work alone and ...
- A group of 21 boys, each working 6 hours a day, complete a school project in 15 days. How many days will it take for 18 boys, working 5 hours daily, to fin...
- A can complete a task in 20 days, and B can complete it in 25 days. When B and C collaborate, they can finish the same task in 75/8 days. Now, if A and C i...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)