Question
In an office, an employee plans to do a work in 16days
with 3 laptops. But after 9 days, he found that only 30% of the work is done with the laptops working for 4 hours a day. If he want to complete the work in the planned time with the laptops, how many hours per day the laptops have to work?Solution
Laptops do 30% of the work in 9 days, or 9 × 4 = 36 hours. So the rest of the (i.e., 70% of the work) can be done in, => (70 × 36)/30 = 84 hours This 84 hours of work has to be done in the remaining (16 – 9) = 7 days. Laptops have to work (84/7) = 12 hours a day to complete the work in the planned time.

Which of the given figures when placed in the 5th position would continue the series that is established by the first four figures?
Select the figure from the alternatives which will complete the pattern in given question figure.
Read the given statements and conclusions carefully. Assuming that the information given in the statements is true, even if it appears to be at varianc...
If the word 'EXAMINATION' is arranged in alphabetical order from the right end, then which of the following letter will be fourth letter to the right of...

Which figure should replace the question mark (?) if the series were to continue?


In each of the following questions, find out which of the answer figures can be formed from the pieces given in the problem figure.