Question
In an office, an employee plans to do a work in 16days
with 3 laptops. But after 9 days, he found that only 30% of the work is done with the laptops working for 4 hours a day. If he want to complete the work in the planned time with the laptops, how many hours per day the laptops have to work?Solution
Laptops do 30% of the work in 9 days, or 9 × 4 = 36 hours. So the rest of the (i.e., 70% of the work) can be done in, => (70 × 36)/30 = 84 hours This 84 hours of work has to be done in the remaining (16 – 9) = 7 days. Laptops have to work (84/7) = 12 hours a day to complete the work in the planned time.
What unique multi-lingual initiatives were launched by CDSL to enhance accessibility in the capital market landscape, and who launched them?
Rakesh Sharma reappointed as MD & CEO of ____________ for a period of 3 years.
The Olympic motto was amended to "faster, higher, stronger - _____________" during the International Olympic Committee's session in Tokyo.
What is a key feature of the revised Pradhan Mantri JI-VAN Yojana approved by the Union Cabinet?
What is the cost of each compressed biogas plant being set up by Reliance Industries in Andhra Pradesh?
Which ruler is credited with founding the Satavahana dynasty?
Which organization developed the Indigenous Technologies of Thermal camera transferred to M/s Aditya Infotech (CP Plus)?
The Indian government aims to extend how much additional credit via guarantees to micro and small enterprises under the CGTMSE scheme over the next two ...
Moody's Investors Service has revised India's growth estimate for 2022 to_______Â from 7 per cent pegged in November 2022.
What challenge continues to delay the finalization of the New Collective Quantified Goal (NCQG) for climate finance?