Efficiency of A is 60% more than B and B takes 32 days to complete a piece of work. A started the work alone and then B joined him 5 days before actual completion of the work. For how many days A worked alone?
More Time and work Questions
- 132 unit of work can be completed by P alone in 22 days. P started working alone and joined by Q after 10 days such that they completed the remaining work ...
- A can complete a work in 30 days. B takes 6 days less than A to complete the same work. In how many days can both of them together complete 60% of the work...
- (y+40) boys can do a piece of work in (z-20) days. (y-5) boys can do the same piece of work in (z+20) days. If (y+30) boys can do the same piece of work in...
- 5 men and 1 boy together can complete a work in 25 days. 3 men and 5 boys can together complete half of the same work in 10 days. Find the time taken by 1 ...
- Anil and Ashish receive Rs.2000 for work of 8 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
- Neha and Seema can finish a work in 10 days and 25 days, respectively, when working alone. Neha started the work. After how many days should Seema join to ...
- Time taken by 'X', 'Y' and 'Z' to finish a task is 48 days, 72 days, and 96 days respectively. All started the task together, but 'X' left 12 days before c...
- A and B together can finish a job in ‘x’ days, while A alone takes ‘x + 32’ days to complete it. B alone can finish the job in 90 days. If C is 20% more ef...
- A and B working together, can do a piece of work in 4(1/2) hours. B and C working together can do it in 3 hours. C and A working together can do it in 2(1/...
- Ram can do a piece of work in 50 days. He alone worked at it for 20 days and then Lakshman completed alone the rest work in 30 days. In how many days, they...