Efficiency of A is 60% more than B and B takes 32 days to complete a piece of work. A started the work alone and then B joined him 5 days before actual completion of the work. For how many days A worked alone?

A 75/13 days
B 89/6 days
C 95/8 days
D 73/5 days
E None of these