Question
Efficiency of A is 60% more than B and B takes 32 days
to complete a piece of work. A started the work alone and then B joined him 5 days before actual completion of the work. For how many days A worked alone?Solution
Efficiency Ratio = A : B = 160 : 100 = 8 : 5 Days Ratio = A : B = 5 : 8 B takes 32 days to complete a piece of work. => 8’s = 32 => 1’s = 4 => 5’s = 20 So A can complete the work in 20 days. Total units of work = 160 (LCM of 20,32) A = 8 unit B = 5 unit A and B worked for 5 days = 5 × (8+5) = 65 units Remaining work = 160 – 65 = 95 units Hence, A worked alone for = 95/8 days.
A loan is categorised as NPA when its interest or principal repayment become overdue for more than 180 days
Which number will come at the end of the number series?
85, 77, 70, 64, 59, 55, _____?
From which state does the distinguished tennis player Rohan Bopanna, who recently retired, originate?
P-Notes are instruments issued by registered FII to overseas investors, who wish to invest in the Indian stock markets without registering themselves w...
Which of the following cities is not situated at the river bank of the Ganges?
In which year were the Operation Shakti nuclear tests conducted by India?
The Government of India launched the PRASAD (Pilgrimage Rejuvenation And Spiritual Augmentation Drive) scheme in the year ____ under the Ministry of Tou...
In which of the following years, progressive liberalisation of the Indian economy was first initiated?Â
Which of the following is correct?
The largest state of the country India is?