      Question

      A, B and C can complete a work in 2 days. If A alone can

      complete the same work in 6 days and B in 4 days, how long will it take for C to finish the work alone?
      A 8 days Correct Answer Incorrect Answer
      B 10 days Correct Answer Incorrect Answer
      C 12 days Correct Answer Incorrect Answer
      D 15 days Correct Answer Incorrect Answer

      Solution

      ATQ: A + B + C = 2 A = 6 B = 4 Total work = 12 (LCM of 2, 6 and 4) A + B + C = 12/2 = 6 A = 12/6 = 2 B = 12/4 = 3 efficiency of C = (6 - (2 + 3)) = 1 Therefore, c will take 12/1 = 12 days