Question
Raju and Raman can complete a piece of work in 12 days
and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?Solution
ATQ,
__________is the process that connects to a network without the use of cables.
If × stands for addition, ÷ stands for subtraction. + stands for multiplication and ̶ stands for division, then what is the value of 20 &t...
A sum of Rs. 663 is divided among X, Y and Z such that X gets Rs. 156 more than Y. Y gets Rs. 78 more than Z. Find the share of Z?
In a mixture 'P', 5 liters of water are replaced with honey, resulting in the mixture containing 55% honey. If the original mixtu...
A ________________ typically connects personal computers within a very limited geographical area, usually within a single building.
Formatting a disk means?
A sum of Rs.8200 is to be divided among 6 brothers, 5 sisters and 2 aunts. If each sister receives thrice as much as each aunt and each brother receives...
Ehsaan is twice as good a worker as Kamal and together they finish a piece of work in 29 days. In how many days will Kamal, working alone, finish the wo...
₹ 1,800 is divided among Nitin, Tushar and Gitanjali. The share of Gitanjali is 5/4 of the sum of the shares of Nitin and Tushar. What is the share of...
The number of five–digit telephone numbers having at least one of their digits repeated is