Question

Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?

A 13(2/3) days
B 13 (1/2) days
C 14 (2/3) days
D 14 (1/3) days