Question
Raju and Raman can complete a piece of work in 12 days and 16 days, respectively. If they work on alternate days, starting with Raju, in how many days will the work be completed?
More Time and work Questions
- The ratio of time taken by P, Q and R to complete work alone is 6:8:3 respectively. If all three together complete the work in 5 days, then find in how man...
- 24 male working 12 hours per day can finish a piece of work in 30 days, while 36 female working 8 hours per day can finish the same work in 60 days. Which...
- A and B together can finish a task in 35 days. If B is 40% more efficient than A, how many days will it take for B alone to complete the task?
- Ajay started a work and left working after 8 days. Vijay finished the remaining work in next 36 days. Had Ajay left the work after working for 12 days then...
- Ravi and Rekha, alone can complete a work in 25 days and 50 days, respectively. They started the work together and left after 10 days such that the remaini...
- Working individually, 'A' can finish 60% of a task in 18 days, and 'B' takes 15 days longer than 'A' to complete the entire task. However, 'B' and 'C' work...
- Pipe 'A' can fill a tank on its own in 14 minutes. When pipes 'A' and 'B' are both opened at the same time, the tank is filled in 18 minutes. Determine how...
- ‘A’ and ‘B’ can do a piece of work in 12 days and 15 days, respectively. If they started the work together and worked on it for 2 days, then find the time ...
- B alone can finish a job in 18 days. A is twice as efficient as B. In how many days can A and B together complete the job?
- X and Y together complete a job in 18 days, while Y alone can do it in 30 days. The ratio of efficiencies of X and Z is 4:5 respectively. What is the ratio...