Question
A question is given, followed by two statements
numbered (I) and (II). You have to decide whether the data provided in the statements is sufficient to answer the question. Read both the statements and select the appropriate answer. Seven persons R, S, T, U, V, W, and X sit in a linear row and face north direction. Who sits immediate right of X? Statements: (I) T sits third to the right of R. Only two persons sit between R and X. S sits immediate left of V. (II) V sits third to the left of U. T sits immediate right of U. X sits second to the left of V.Solution
From statement I alone, T sits third to the right of R. Only two persons sit between R and X. S sits immediate left of V. We get: Case 1: X S V R U/W W/U T Case 2: X U/W W/U R S V T As, from the information given in statement I, we cannot determine the person, who sits immediate right of X. So, data in statement I alone is not sufficient to answer the question. From statement II alone, V sits third to the left of U. T sits immediate right of U. X sits second to the left of V. We get: X _____V ______ ______ U T The positions of R, S and W, cannot be determined. So, we cannot determine the person, who sits immediate right of X. Combining statements I and II together, we get: X S V R W U T So, combining statements I and II together, we get S sits immediate right of X. Therefore, data in statements I and II together is sufficient to answer the question
'Akshay' alone can do a piece of work in 25 days. 'Ben' alone takes 40 days to do the same work. How much 'Akshay' should be paid out of total wages of ...
X men can complete the piece of work in 36 days and (X + 30) men can complete the same work in 15 days less than that of days taken by X men. Find the v...
A and B together can complete a work in 20 days. After working together for 8 days, B leaves, and A completes the remaining work in 16 more days. In how...
P can do a piece of work in 25 days, Q can complete double the work in 40 days and R can do the work in 30 days. If all of them together earn Rs. 7400, ...
A and B together can finish a job in ‘x’ days, while A alone takes ‘x + 32’ days to complete it. B alone can finish the job in 90 days. If C is ...
Suraj is one third as good as workman as Pankaj and together they finish a piece of work in 36 days. The number of days taken by Suraj alone to finish t...
A certain Sales target was assigned to a team of men to complete in 18 days. But 8 men did not turn up for the target and the rest men complete the sale...
N workers can complete a piece of work in 50 days. When 5 more workers joined, then the work got completed in 40 days, then what is the value of N?
Anil can do a piece of work in 25 days. He alone worked at it for 10 days and then Sunil completed alone the rest work in 15 days. In how many days, the...
‘A’ alone can complete a work in 10 days. ‘B’ alone can complete the same work in 20 days. If ‘A’ and ‘B’ work together for 3 days, then...