Question
Akhil and Nikhil together can complete a work in 12 days while Nikhil alone takes 18 days to complete 30% of the work. If the efficiency of Sachin is 25% more than that of Akhil, then find the time taken by Sachin alone to complete the whole work.
More Time Questions
- A, B and C can do a piece of work in 11 days, 20 days and 55 days respectively. If B works daily and is supported by A and C on alternate days beginning wi...
- A is thrice as efficient as B and can finish a piece of work in 28 days less than B. B can finish this work in how many days?
- 3 men dig a hole in 10 days. How many days would it take for 5 men to dig the same hole ?
- A’ and ‘B’ together can complete a work in 8 days, while ‘B’ and ‘C’ together can complete the work in 12 days. I...
- The diameters of three inlet pipes of a cistern are 1.5 cm, 2 cm and 2.5 cm respectively. The pipe with the maximum diameter can alone fill up the cistern ...
- A and B can complete a task in 25 days. B alone can complete 33 1/3 % of the same task in 15 days. In how many days can A alone complete 4/15th of the sam...
- A man is travelling at a speed of 100 km/h such that he will take 60 minutes to reach his destination. But after completing half the journey, the man took ...
- Pipe A can fill the tank 5 times faster than pipe B, if pipe A and B together fill the tank in 50 minutes, then pipe B alone can fill the tank in:
- Two trains of length 200m and 160m respectively are running on parallel lines of rails. When running in the same direction the faster train passes the slow...
- Three pipes, A, B, C can fill an empty cistern in 2, 3 and 6 hours respectively. They are opened together. After what time should B be closed, so that the ...
Relevant for Exams:
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt