Question
A contractor undertook to do a work in 60 days and
employed 30 men to do it. After 45 days he found that only `3/5` th of the work was done. How many more men must be employed so that the work may be finished in time?Solution
Applying chain rule, (45 x 30)/(3/5) = (M2 x 15)/(2/5) Mâ‚‚ = (5 x 45 x 30 x2)/(15 x 5 x 3) = 60 men Required men = 60 – 30 = 30 men
World Lion day is observed every year on?
What is the name of the app that serves as an all-in-one source for detailed air quality data, real-time pollution levels, health tips, and allows users...
Consider the following statements about Pong Dam Lake Wildlife Sanctuary:Â
1.     Recently Ministry of Environment declared a one-kilometr...
Who is named as the new Chairman and CEO of the Railway Board?
Who has been appointed Deputy National Security Adviser to handle internal affairs?
Who is the newly appointed Managing Director & Chief Executive Officer of SBI Capital Markets?
Recently Khelo India Youth Games started in which of the following states?
Consider the following statements:
I. For the purpose of effective utilization of Remote Sensing and Geographic Information System technology (GI...
What is the Government of India’s Revenue from Operations target for IREDA in FY 2025–26, as per its MoU with MNRE?
What is the theme of the 4th World Statistics Day to be celebrated in 2025?