Question
18 workers can complete a project in 15 days. How many additional workers are needed to complete the same project in 9 days, working at the same rate?
More Time and work Questions
- A and B together can complete a work in 12 days, and B alone can complete it in 20 days. How many days will A take to complete the work alone?
- ‘A’ and ‘B’ can do a piece of work in 30 days and 40 days, respectively. They started working together but ‘A’ left after 9 days. Find the time taken by ‘B...
- 'A' and 'B' together can do a piece of work in 12 days while 'B' and 'C' together can do the same work in 20 days. 'A' started the work alone and worked on...
- ‘A’ alone can complete a work in 50 hours. ‘A’ started the work alone and left after working on it for 20 hours. If ‘B’ completed the rest of the work in 1...
- P and Q individually can complete the work in 26 days and 39 days respectively. If the time taken by R alone to complete the work is 1.25 times the time ta...
- Sachin can complete a job in 15 days. Ankit alone can complete the same job in 10 days. Sachin works for 9 days and then the remaining job is completed by ...
- A and B can complete a work together in 20 days. If A alone can complete one-fourth of the work in ‘x’ days and remaining work is completed by B alone in 3...
- Virat can do a piece of work in 28 days and Sachin can do the same work in 42 days. If Virat works for 4 days and got Rs. 1800, and the remaining work will...
- A and B can complete a work together in 30 days. If A alone can complete one-third of the work in ‘x’ days and remaining work is completed by B alone in 2x...
- Anuj can complete a certain piece of work in 25 days by taking rest for 9 hours daily. If he rests twice as much as before and also works twice as fast, th...
Hey! Ask a query
Please enter email id
The email must be a valid email address.
Please enter Mobile Number
Please enter valid Mobile Number
Please enter your Doubt
Think You're Ready for RBI Grade B?
RBI Grade B 2026 Phase 1 Memory Based Paper
- 200 Questions with Detailed Solutions
- Section-wise Coverage (GA, English, Quant & Reasoning)