Question
A, B and C can complete a piece of work in 12 days, 18 days and 36 days respectively (working alone). They all start working together. After 2 days, C leaves the work. After another x days, B also leaves the work, and the remaining work is completed by A alone in 3 more days. In how many days in total was the work completed (from the start)?
Solution
Let total work = 1 unit. Rates per day: A: 1/12 B: 1/18 C: 1/36 First 2 days: A + B + C Combined rate = 1/12 + 1/18 + 1/36 LCM = 36 = (3 + 2 + 1)/36 = 6/36 = 1/6 Work in first 2 days = 2 Γ 1/6 = 1/3 Remaining work = 1 β 1/3 = 2/3 Next x days: only A + B Rate (A + B) = 1/12 + 1/18 LCM = 36 β (3 + 2)/36 = 5/36 Work in these x days = x Γ 5/36 Last 3 days: only A Work by A alone in last 3 days = 3 Γ 1/12 = 3/12 = 1/4 Now total work: (First part) + (Second part) + (Third part) = 1 1/3 + (5x/36) + 1/4 = 1 Take LCM 36: 1/3 = 12/36 1/4 = 9/36 So: (12/36) + (5x/36) + (9/36) = 1 (21 + 5x)/36 = 1 21 + 5x = 36 5x = 15 x = 3 Total time = 2 (first phase) + 3 (second phase) + 3 (last phase) = 8 days.
- Anupam requires 30% more time than Aman to complete a certain task. If both of them work together and earn a total of Rs. 23,000, determine Anupam's share ...
- A can do a job alone in 66 days, B can do it alone in 55 days, while A, B, and C working together can complete the job in 11 days. In how many days can C d...
- A can complete a task in 20 days, and B can complete it in 25 days. When B and C collaborate, they can finish the same task in 75/8 days. Now, if A and C i...
- A can complete a work in 15 days and B can complete the same work in 20 days. They work together for 5 days. If after that B's efficiency increases by 25%,...
- Anupam can do a piece of work in 36 days and Rajveer can do it in 15 days. Diksha can do the same work in (17/18) times the number of days required by both...
- Two pipes X and Z can fill a tank in 36 hours and 48 hours respectively, while pipe Y can drain the tank in 72 hours. If pipes X and Z are opened together ...
- A, B and C can complete a work in 15, 20 and 30 days respectively. They all start working together. After 3 days, C leaves. The remaining work is completed...
- Anil and Ashish receive Rs.2000 for work of 8 days. If Anil is 4 times efficient than Ashish, then find the daily wage received by Ashish.
- A and B individually can complete the work in 20 days and 30 days respectively. If the time taken by C alone to complete the work is 1.25 times the time ta...
- Working alone, 'C' can complete a job in 30 days. 'D' takes 20% less time than 'C' to finish the same job. Calculate the percentage of work done by 'C' and...