Question
A can complete a work in 24 days, B in 36 days and C in 48 days. All three start working together. After 4 days, A leaves the work. B and C continue the work for 6 more days. The remaining work is completed by B alone. In how many days did B alone complete the remaining work?
Solution
A's 1-day work = 1/24 B's 1-day work = 1/36 C's 1-day work = 1/48 (A + B + C)'s 1-day work = 1/24 + 1/36 + 1/48 = 6/144 + 4/144 + 3/144 = 13/144 Work done in 4 days = 4 Γ 13/144 = 52/144 = 13/36 Remaining work = 1 - 13/36 = 23/36 Now, B + C work for 6 days. (B + C)'s 1-day work = 1/36 + 1/48 = 4/144 + 3/144 = 7/144 Work done in 6 days = 6 Γ 7/144 = 42/144 = 7/24 Remaining work after that = 23/36 - 7/24 = 46/72 - 21/72 = 25/72 B alone does 1/36 work per day. Required time = (25/72) Γ· (1/36) = (25/72) Γ 36 = 25/2 = 12.5 days Hence, the correct answer is 12.5 days.
- Karan, Arjun and Krunal alone can complete a work in 40, 60 and 48 days respectively. All of them started working together but after 3 days from start Kara...
- Rajesh and Bhupesh can complete a piece of work in 20 days and Bhupesh alone in 25 days. In how many days can Rajesh alone complete the work?
- A worker completes 30% of a job in 6 days. Assuming the same rate of work, in how many total days will he complete the whole job?
- In an office, an employee plans to do a work in 20 days with 6 laptops. But after 10 days, he found that only 40% of the work is done with the laptops work...
- 35 men can complete a piece of work in 40 days. βxβ men started the work and after 30 days 60 more men joined them so that whole work was finished in the d...
- A can complete a piece of work in 24 days. He worked for 21 days and then B finished the remaining work in 6 days. In how many days can A and B finish the ...
- Arjun and Karan can do a work separately in 20 days and 50 days respectively. Arjun started the work and was later joined by Karan. When should Karan join ...
- Working alone, B can complete the work in 30 days. C is twice as efficient as B and A takes 20 days more than it takes C to complete the work. Working toge...
- 50% of the work done by Meena in 2 days is equal to 25% of the work done by Lata in 5 days. If Meena can complete the job alone in 10 days, then how long w...
- Ten men begin to do work. But after some days, four of them left the job. As a result, the job that could have been completed in 40 days is completed in 50...