Question
Alex and Ben can complete a job individually in 14 days and
21 days, respectively. If they take turns to work one day each, beginning with Alex, how long will it take to complete the entire task?Solution
ATQ,
Let total work = 42 units (LCM of 14 and 21)
Alex’s efficiency = (42 ÷ 14) = 3 units/day
Ben’s efficiency = (42 ÷ 21) = 2 units/day
Work in 2 days = 3 + 2 = 5 units
Time = (42 ÷ 5) × 2 = 16.8 days
Between which two rivers was the ancient city of Takshashila located?
Which of the following statements is correct?
(i) The elevation of this mountain range is approximately 1000-1500 meters.
(ii) The climati...
G-77 summit is a forum of :
Who is the present Human Resource Development minister in INDIA?
Where is the Virupaksha temple located?
Who established the non-governmental organization Hitaishi India?
The Triple Talaq Case (2017) declared instant Triple Talaq:
The State Election Commission in Uttar Pradesh was established for the elections of panchayats and urban bodies in :
Earth's Rotation Day is commemorated on which date every year?
Match the following