Question
Alex and Ben can complete a job individually in 14 days and
21 days, respectively. If they take turns to work one day each, beginning with Alex, how long will it take to complete the entire task?Solution
ATQ,
Let total work = 42 units (LCM of 14 and 21)
Alex’s efficiency = (42 ÷ 14) = 3 units/day
Ben’s efficiency = (42 ÷ 21) = 2 units/day
Work in 2 days = 3 + 2 = 5 units
Time = (42 Ă· 5) Ă— 2 = 16.8 days
What is the main component of natural gas?
What state ranked as the top electronics exporter in India during the fiscal year 2022-2023?
What was the headline inflation rate in India for 2023-24 as per the RBI Annual Report 2023-24?
Which article can not be suspended even during the Emergency ?Â
In Uttar Pradesh, Academy of Fine Arts is located in?
In which country is the Wimbledon tennis competition organized?
Recently PM launched “PM-Shri” Yojana, it is associated with?
The 2025 Asian Youth Para Games will be hosted in _____________.
Who is the author of the book “Neel Darpan ”?
What is the run-off factor that RBI plans to enforce on digitally accessible retail deposits?