Aman and Bheema together can
finish 50% of a task in 12 days, while Chinky alone can finish 30% of the same task in 12 days. Determine the time required for Aman, Bheema, and Chinky together to complete the entire task.Solution
ATQ,
Time taken by ‘Aman’ and ‘Bheema’ together to complete the whole task = (12/0.5) = 24 days Time taken by ‘Chinky’ to complete the whole task = (12/0.30) = 40 days Let total task be 120 units {LCM of 24 and 40} Efficiency of ‘Aman’ and ‘Bheema’ together = (120/24) = 5 units/day Efficiency of ‘Chinky’ alone = (120/40) = 3 units/day Required time = 120/(5 + 3) = 15 days
How many students not appeared in exam Y?
Calculate the total revenue generated from each clothing item over the six-month period. Based on this data, determine the overall profit or loss for th...
Find the number of female employees working in company C.
A started a business with an investment of Rs.1200. After some months, B joins the business with an investment of Rs.3600 and after two more months C jo...
- Find the difference between number of silk flowers sold by shop A and B.
On Sunday, Chocolate cookies sold are 9 times as compare to Butter cookies on same day. Sold Butter cookies are less than unsold Butter cookies. If pric...
Number of males of tribe Raba is what percentage more than the number of males of tribe Dimasa?
What percentage more are the number of jasmine flowers in Garden 'C' compared to the number of rose flowers there?
Find the number of Red apples sold by ‘S’
Find the total time taken by boat C to cover the entire journey?